Project Description

Client
Wintertide Ltd ( Road to be taken in charge by Dublin City Council)
Designer
Roughan & O'Donovan

These works have been undertaken to construct a new street from North Wall Quay to Sherriff's Street.

Key Elements

  • Construction of 300m of a new street including all earthworks and pavement layers
  • Installation of new services including communications, ESB, district heating, watermains, foul sewer, traffic lighting and public lighting
  • Extensive granite paving and kerbing used throughout the works
  • Trenchless installation of all services underneath the LUAS on Mayor Street
  • Liaising with Dublin City Council to obtain the various licences required to undertake the works
  • Demolition works on a number of buildings and walls in advance of the works
  • New drainage installed for full length of the scheme and connection into existing network
  • Construction of 3 new junctions, on North Wall Quay, Mayor Street and Sherriff's Street including traffic signals
  • All traffic signs and road marking installed as part of the works, including alterations to existing road markings at interfaces
  • Construction of new cycletrack and footpaths including tie ins to existing works