Project Description

Consultant
Hanley Pepper

This project was undertaken to install a new watermain and power supply for a new data centre

Key Elements

  • Design and implementation of pedestrian and traffic management on the public road to allow installation of the new power ducting
  • Design and installation of pedestrian and traffic management within the business park to install the new watermain
  • Liaising with South Dublin County Council to obtain a road opening licence and associated T2 licences
  • Installation of power ducting along the public road requiring reinstatement of green areas, concrete footpaths and crossing under an existing stream
  • Liaising with the ESB to agree the installation of the ducting, construction of the new substation and mini pillars
  • Construction of new watermain chambers constructed in situ along the existing watermain line
  • Installation of new watermain and all associated valves, hydrants and chambers
  • Liaising with the ESB to agree the installation of the new power ducting and working in the vicinity of transmission lines