Project Description

Client
Dublin and Dun Laoghaire ETB
Designer
DBFL Consulting Engineers
Location
Citywest, Dublin 24

This scheme was undertaken to improve the pedestrian and cyclist facilities to provide access to a new school

Key Elements

  • Installation of a new signalised junction and installation of new signal poles, heads and controllers
  • Liaising with the Local Authority (SDCC) to obtain the road opening and traffic management licence
  • Installation of high fricition surfacing on all approach roads
  • Realignment of kerbing on all approaches to the junction
  • Reinstatement of the footpath and grass verge on completion of the ducting installation