This project has been undertaken to construct a regional attenuation pond to attenuate drainage water prior to discharge into the Brides Glen Stream.
Project Description
Client
Dun Laoghaire Rathdown County Council
Designer
Roughan & O'Donovan Consulting Engineers
Location
Cherrywood Business Park, Cherrywood, Co Dublin
Key Elements
- Earthworks to excavated the new attenuation pond and reinstatement the temporary pond that was in place during the construction of the Cherrywood Business Park
- Diversion of significant services including HV ESB and a trunk watermain
- Construction of a new footpath and cycletrack alongside the pond
- Installation of new public lighting