Project Description

Client
Laois County Council
Consultant
RPS Consulting Engineers
Location
Maidenhead, Co. Laois

This scheme has been undertaken to realign the existing N80 at Maidenhead for a distance of 2km

Key Elements

  • Design and implementation of pedestrian and traffic management during construction
  • Bulk earthworks activities including cut and fill activities
  • Installation of new drainage network including attenuation systems
  • Construction of all pavement layers
  • Working both on and off line to construct the new alignment
  • Installation of new ducting for utility diversions
  • Installation of 4 no. culverts including for the Coolanknowle stream
  • Installation of new access underpass
  • Installation of new safety barrier
  • Installation of all new road signs and markings associated with the scheme